Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?
Full set: 132 questionsThe PRINCE2 principle of 'defined roles and responsibilities' ensures that the project management team structure represents the three primary stakeholder interests: business, user, and supplier. The Project Board is specifically structured to embody this, with the Executive representing the business interest, the Senior User representing the user interest, and the Senior Supplier representing the supplier interest. This structure ensures that the right people are involved in directing and managing the project, providing a clear framework for stakeholder engagement and decision-making.
B. 'Continued business justification' is the principle that ensures a project remains desirable, viable, and achievable, which is a key concern for the business stakeholder.
C. 'Learn from experience' is the principle focused on continuous improvement throughout the project lifecycle, not the structure of stakeholder engagement.
D. 'Tailor to suit the project' is the principle of adapting PRINCE2 to the specific project environment, which includes how roles are implemented, but 'A' is the core principle.
- AXELOS. (2018). PRINCE2 Agile® Foundation. TSO (The Stationery Office). Section 5.3.4, p. 38. "A PRINCE2 project team has defined roles and responsibilities within an organization structure that engages the business, user and supplier stakeholder interests."
- AXELOS. (2018). PRINCE2 Agile® Foundation. TSO (The Stationery Office). Section 7.2.1, p. 52. (Describes the composition of the Project Board representing these three interests).
Keep practicing
Take the free AGILE-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILE-FOUNDATION practice questions
- Question 1When tracking progress, which term describes using agile techniques at the delivery level…
- Question 2Which statement describes the Kanban approach?
- Question 3Which of the following is an example of 'being agile' rather than just ‘doing agile’?
- Question 4What is the purpose of the 'progress' practice?
- Question 5To help with prioritization, what is MOST important when understanding the difference bet…
- Question 6What is the MOST important when blending PRINCE2 Project Management with agile?