AGILEBA-FOUNDATION practice question 8 of 10

During the Foundations phase, how is the Prioritised Requirements List used for Requirements Planning?

Full set: 50 questions
Answer options
A: Requirements allocated to each Development Timebox are arranged into a Story Map
B: Requirements are broken down into tasks and prioritised
C: Requirements are displayed on a Story Board for visibility
D: Requirements and priorities are negotiated to allow the first increment to be planned Correct answer
Correct Answer:
D. Requirements and priorities are negotiated to allow the first increment to be planned
Explanation

During the Foundations phase, the Prioritised Requirements List (PRL) is a key input for planning the first project increment. The Agile BA facilitates discussions with business and technical stakeholders to review, refine, and negotiate the requirements and their MoSCoW priorities. This collaborative process ensures that a realistic and valuable set of features is agreed upon for delivery in the first increment, forming the basis of the Delivery Plan.

Why Incorrect

A. Story Mapping is a technique used to visualise and structure the PRL, but the core activity is the negotiation of scope for the plan.
B. Breaking requirements into tasks occurs during Timebox planning within the Evolutionary Development phase, not during the high-level Foundations phase.
C. A Story Board is a tool used to track work in progress during a Timebox, which happens in the Evolutionary Development phase.

References

- Agile Business Consortium. (2017). Agile Business Analysis (AgileBA®) Handbook v2. Chapter 5, The DSDM Process, Section 5.5, Foundations. This section describes how the products from this phase, including the baselined PRL, form the foundation for development.