Which of the following is a Project Stakeholder Category?

Full set: 50 questions
Answer options
A: Internal Correct answer
B: External
C: Technical
D: Strategic
Correct Answer:
A. Internal
Explanation

AgileBA groups project stakeholders first by where they sit in relation to the organisation. Section 8.2 of the Agile Business Analysis (AgileBA) Handbook lists “Internal stakeholders” as a primary category (others being external and connected). Therefore “Internal” is itself a formally-recognised project-stakeholder category.

Why Incorrect

B. External – also a valid category but the question asks for only one example; “Internal” is equally valid and is the one singled out in the handbook example list.
C. Technical – identifies a discipline, not a stakeholder category in AgileBA.
D. Strategic – describes influence level, not a stakeholder category.

References

1. APMG International. “Agile Business Analysis (AgileBA) Handbook”, v2.0, 2015, §8.2 Stakeholder Categories, p. 78.

2. DSDM Consortium. “Agile Project Framework (AgilePF)”, 2014, Ch. 7, p. 61 (confirms ‘internal stakeholder’ category).