AGILEPM-PRACTITIONER practice question 6 of 25
During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re- engage this group and explore discrepancies in understanding. Is this an appropriate application of Agile Project Management for this project?
Full set: 185 questionsA Facilitated Workshop is a specialized, interactive session designed to achieve a specific outcome, such as building a shared understanding, generating ideas, or making decisions. In this scenario, the disagreement about the Timebox outcome indicates a lack of shared understanding among stakeholders. Using a workshop is an excellent application of the DSDM collaborative approach to bring the group together, discuss the discrepancies, and forge a consensus. This proactive problem-solving aligns with the AgilePM principles of 'Collaborate' and 'Communicate continuously and clearly'.
A. Progress reports are typically handled in other forums like Daily Stand-ups or checkpoints, not the primary goal of a workshop for resolving conflict.
C. Escalation should not be the first step. The Project Manager is empowered to resolve issues at the lowest possible level, and a workshop is an appropriate tool for this.
D. Daily Stand-ups are for the Solution Development Team to coordinate daily work, not for in-depth stakeholder requirement clarification or conflict resolution.
APMG International
"AgilePM® Agile Project Management Handbook v2
" (2014)
Chapter 15: DSDM Products
Section 15.10 Facilitated Workshops
p. 93.
APMG International
"AgilePM® Agile Project Management Handbook v2
" (2014)
Chapter 10: DSDM Techniques
Section 10.2 Facilitated Workshops
pp. 61-62.
APMG International
"AgilePM® Agile Project Management Handbook v2
" (2014)
Chapter 6: The DSDM Principles
Principle 3: Collaborate
p. 20.
Keep practicing
Take the free AGILEPM-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILEPM-PRACTITIONER practice questions
- Question 1The Legal Specialist has reviewed the plans for the rebranding work and has assessed how …
- Question 2The Solution Development Team are progressing through the first Structured Timebox. What …
- Question 3Using the information provided in the additional information, answer the following questi…
- Question 4Using the information provided in the additional information, answer the following questi…
- Question 5Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate So…
- Question 7Which Facilities stakeholder is MOST likely to be placed within the ‘external’ segment fo…