AGILEPM-PRACTITIONER practice question 2 of 25
The Solution Development Team are progressing through the first Structured Timebox. What should the Project Manager do to lead the team at this time?
Full set: 185 questionsDuring a Timebox, the Project Manager's role shifts from director to facilitator and leader. They must protect the Solution Development Team from distractions while remaining available to remove impediments. The Daily Stand-up is a key ceremony for the PM to monitor progress and identify blockers without actively participating. The correct protocol is for the PM to attend as an observer and then address any problems or issues that require their intervention after the meeting has concluded. This respects the team's ownership of the meeting while allowing the PM to effectively support them.
A. This describes a command-and-control management style, which is inappropriate for an Agile project where the team is empowered.
B. The Project Manager has a crucial role in removing blockers and managing risks; doing nothing would be an abdication of responsibility.
D. The Solution Development Team owns and updates the Team Board; it is not the Project Manager's responsibility to maintain it.
- APMG International
"AgilePM® Agile Project Management Handbook v2.0
" 2014
p. 60
Section 10.4
The Project Manager (describes the role as a facilitator and leader).
- APMG International
"AgilePM® Agile Project Management Handbook v2.0
" 2014
p. 98
Section 14.5.3
Daily Stand-Ups ("The Project Manager... should attend as an observer... Any problems that are highlighted... should be dealt with outside of this meeting").
Keep practicing
Take the free AGILEPM-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILEPM-PRACTITIONER practice questions
- Question 1The Legal Specialist has reviewed the plans for the rebranding work and has assessed how …
- Question 3Using the information provided in the additional information, answer the following questi…
- Question 4Using the information provided in the additional information, answer the following questi…
- Question 5Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate So…
- Question 6During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome …
- Question 7Which Facilities stakeholder is MOST likely to be placed within the ‘external’ segment fo…