AGILEPM-PRACTITIONER practice question 2 of 25

The Solution Development Team are progressing through the first Structured Timebox. What should the Project Manager do to lead the team at this time?

Full set: 185 questions
Answer options
A: Maintain a tight control on progress, recording all discussions and making all decisions.
B: The Project Manager should do nothing during a Timebox.
C: Attend the Daily Stand-up and discuss any problems at the end. Correct answer
D: Update the Team Board with a summary of team progress and the current status of work.
Correct Answer:
C. Attend the Daily Stand-up and discuss any problems at the end.
Explanation

During a Timebox, the Project Manager's role shifts from director to facilitator and leader. They must protect the Solution Development Team from distractions while remaining available to remove impediments. The Daily Stand-up is a key ceremony for the PM to monitor progress and identify blockers without actively participating. The correct protocol is for the PM to attend as an observer and then address any problems or issues that require their intervention after the meeting has concluded. This respects the team's ownership of the meeting while allowing the PM to effectively support them.

Why Incorrect

A. This describes a command-and-control management style, which is inappropriate for an Agile project where the team is empowered.
B. The Project Manager has a crucial role in removing blockers and managing risks; doing nothing would be an abdication of responsibility.
D. The Solution Development Team owns and updates the Team Board; it is not the Project Manager's responsibility to maintain it.

References

- APMG International

"AgilePM® Agile Project Management Handbook v2.0

" 2014

p. 60

Section 10.4

The Project Manager (describes the role as a facilitator and leader).

- APMG International

"AgilePM® Agile Project Management Handbook v2.0

" 2014

p. 98

Section 14.5.3

Daily Stand-Ups ("The Project Manager... should attend as an observer... Any problems that are highlighted... should be dealt with outside of this meeting").