APM-PFQ practice question 5 of 35

What aspect is important to clarify when conducting scope definition?

Full set: 409 questions
Answer options
A: The number of products contained in the PBS,
B: The boundaries and interfaces with adjacent projects. Correct answer
C: Who is going to perform the work.
D: When the work is going to be performed.
Correct Answer:
B. The boundaries and interfaces with adjacent projects.