APM-PFQ practice question 6 of 35

Which of the following are documented in a risk register? 1) Analysis 2) Priority 3) Ownership 4) Responses

Full set: 409 questions
Answer options
A: 1, 3 and 4
B: 1, 2 and 4
C: 1, 2 and 3
D: 2, 3 and 4 Correct answer
Correct Answer:
D. 2, 3 and 4