Which of the following is true regarding differences between linear and iterative life cycles?

Full set: 409 questions
Answer options
A:

A. A linear life cycle is best for evolving projects whereas an iterative life cycle is better for more structured projects.

B:

B. A linear life cycle is sequential whereas an iterative life cycle repeats one or more phases.

C:

C. A linear life cycle is always longer in duration whereas an iterative life cycle is always shorter in its duration.

D:

D. A linear life cycle is formally managed by dedicated project manager whereas management responsibility is shared in an iterative life cycle