ASF practice question 2 of 15

A team selects a Product Backlog Item (PBI) for the Sprint Backlog. What must a team do to finish the Product Backlog Item it selects?

Full set: 59 questions
Answer options
A: As much as can be done in the Sprint before the deadline.
B: As much as is required to satisfy the definition of 'done'. Correct answer
C: Analyze, design, program, test and document the PBI.
Correct Answer:
B. As much as is required to satisfy the definition of 'done'.