ASF practice question 6 of 15
During a Sprint Planning session, the team argues about the work estimates for a particular story. The Product Owner estimates five days. The Lead…
Choose your answer, then check it against the explanation.
During a Sprint Planning session, the team argues about the work estimates for a particular story.
The Product Owner estimates five days.
The Lead Architect estimates two days.
The Scrum Master estimates eight days.
The team member working on it estimates seven days.
What value (in days) should be used for planning?
Question 6 of 15
Keep practicing
Take the free ASF practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ASF practice questions
- Question 1What is an "escaped defect"?
- Question 2A team selects a Product Backlog Item (PBI) for the Sprint Backlog. What must a team do t…
- Question 3Which statement describes Release Planning?
- Question 4A Manager requests to attend the daily stand-up meeting so that he can be more responsive…
- Question 5The Product Owner is going on a three-week vacation. The team should be closing the curre…
- Question 8What message can you give to a customer about a key benefit of using Scrum?