ASF practice question 5 of 15

The Product Owner is going on a three-week vacation. The team should be closing the current Sprint and starting a new Sprint at the end of the first week of the Product Owner's vacation. What is the best way to continue the Scrum rituals in this situation?

Full set: 59 questions
Answer options
A: Each Scrum team should ideally have two Product Owners to provide cover.
B: The Product Owner should be requested to delay his vacation by a week.
C: The Scrum Master should take over and cover for the Product Owner. Correct answer
Correct Answer:
C. The Scrum Master should take over and cover for the Product Owner.