BUSINESS-ANALYST practice question 21 of 35

Northern Trail Outfitters (NTO) has completed a project with a third-party event organization platform to enhance its MVP Experience Site. Many…

Full set: 310 questions
Northern Trail Outfitters (NTO) has completed a project with a third-party event organization platform to enhance its MVP Experience Site. Many features were left in the project backlog. NTO's IT team is beginning a new phase of work on the Experience Site to build additional features requested by business stakeholders and wants to include the items that were left in the backlog in the first phase. How should the business analyst coordinate the user stories to most efficiently manage the new project timeline?
Answer options
A: Include existing and new user stories to be completed within the duration of the project. Hire additional developers to accommodate both work streams to prevent delays within the schedule sprints.
B: Reprioritize existing and new user storks to place the stories into each sprint of the project. Return an equivalent: amount of lower priority work to the project backlog, Correct answer
C: Prioritize user stories for the new enhancements for the initial sprints of the project to accommodate business stakeholder requests. Complete existing user stories in the final sprint of the project.
Correct Answer:
B. Reprioritize existing and new user storks to place the stories into each sprint of the project. Return an equivalent: amount of lower priority work to the project backlog,
Explanation

The most efficient and standard Agile approach is to treat all work items, whether new or from a previous phase, as a single product backlog. The business analyst's role is to facilitate the reprioritization of this consolidated backlog with business stakeholders based on current business value. The highest-priority stories are then selected for upcoming sprints. This ensures the team is always working on the most valuable features. Acknowledging that some lower-priority items may be returned to the backlog is a key part of managing scope and expectations within a fixed timeline.

Why Incorrect

A. Hiring more developers is a resource-based solution and may not be feasible or efficient; the BA's role is to manage the backlog and priority first.
C. Prioritizing based on whether a story is "new" or "existing" is arbitrary and ignores the actual business value, which should be the sole driver of priority.

References

1. Salesforce Trailhead, Backlog Management module, "Prioritize Your Backlog" unit. This unit emphasizes that a backlog is a living document and that prioritization is a continuous activity based on value, risk, and dependencies, not the age of the user story.

2. Salesforce Architects, Well-Architected - Agile Delivery, "Backlog Management". This guide states, "The product backlog is an ordered list of everything that is known to be needed in the product... The Product Owner is responsible for the Product Backlog, including its content, availability, and ordering." This implies a single, prioritized list for all work.