CBAP practice question 28 of 35

A business analyst (BA) has recently completed a comprehensive stakeholder analysis. Next the BA would like to consider ways in which to ensure that…

Full set: 494 questions
A business analyst (BA) has recently completed a comprehensive stakeholder analysis. Next the BA would like to consider ways in which to ensure that the stakeholders remain engaged throughout the change strategy. Some of the considerations include timing and frequency, location, available tools, delivery methods and the stakeholders' preferences. In which of the following plans would the BA document these considerations?
Answer options
A: Stakeholder Collaboration Plan
B: Business Analyse Plan
C: Stakeholder Analysis Plan
D: Communications Management Plan Correct answer
Correct Answer:
D. Communications Management Plan
Explanation

A communications management plan is a document that describes how the business analyst will communicate with the stakeholders throughout the project. It includes information such as the timing and frequency of communication, the location and mode of communication, the tools and techniques to be used, the delivery methods and formats, and the stakeholders’ p

References

and

needs. A communications management plan helps to ensure that the stakeholders are informed,

engaged, and satisfied with the project progress and outcomes. A stakeholder collaboration plan is a

document that describes how the business analyst will collaborate with the stakeholders to elicit,

analyze, validate, and manage the requirements. A business analysis plan is a document that

describes how the business analyst will conduct the business analysis activities, such as the scope,

approach, deliverables, tasks, resources, and schedule. A stakeholder analysis plan is a document

that describes how the business analyst will identify, analyze, and prioritize the stakeholders and

their needs, expectations, and influence. Reference: BABOK Guide v3, Chapter 2: Business Analysis

Planning and Monitoring, Section 2.5: Plan Business Analysis Communication, p. 38-40; Chapter 3:

Business Analysis Governance and Information Management, Section 3.1: Plan Business Analysis

Governance, p. 50-51.