A service company conducted a change management project to increase customer satisfaction for one year. What can be done to sustain the positive trend on customer satisfaction observed during the project?

Full set: 150 questions
Answer options
A: Design and conduct a lessons learned evaluation at the end of the project and share improvements for future change programs
B: Change objectives and goals focused on improving customer satisfaction Correct answer
C: Revise the current vision statement to include a focus on customer satisfaction
D: Change current communications channels, tools and methods to focus on customer satisfaction
Correct Answer:
B. Change objectives and goals focused on improving customer satisfaction
Explanation

To sustain a change, the new behaviors and desired outcomes must be integrated into the organization's standard operating procedures and systems. Changing objectives and goals to focus on customer satisfaction directly embeds the project's successful outcome into the performance management system. This creates ongoing accountability, provides a mechanism for continuous measurement, and formally signals to employees that the new focus is a permanent priority. This process of integration is a critical component of making a change "stick" and ensuring it becomes part of the organization's "business as usual" operations.

Why Incorrect

A. A lessons learned evaluation is a project closure activity focused on improving the process for future change initiatives, not on sustaining the outcome of the current one.
C. Revising the vision statement is a high-level strategic action. While powerful, it may not be necessary if the existing vision already supports customer focus. Changing operational goals is a more direct and concrete sustainment action.
D. While ongoing communication is crucial for sustainment, this option focuses on changing the channels and tools, which is a tactical choice and less impactful than structurally embedding the change into performance goals.

References

1. The Standard for Change Management. (2014). Association of Change Management Professionals (ACMP).

Section 4.5, Sustain Outcomes: This section details the process of ensuring the change is sustained. A key activity listed is to "Integrate the change into 'business as usual' (BAU) operations and culture." This explicitly includes "Revising performance management and reward systems to align with the change." Option B is a direct application of this principle. The Standard clearly separates this sustainment activity from project closure activities like lessons learned (covered in Section 5.0).

2. Kotter, J. P. (2012). Leading Change. Harvard Business Press.

Chapter 10, Step 8: Anchoring New Approaches in the Culture: Kotter emphasizes that for change to be sustained, it must become "the way we do things around here." He states that this requires showing people how the new behaviors and attitudes have improved performance and ensuring that the next generation of management personifies the new approach. Aligning official objectives and goals (Option B) is a primary mechanism for anchoring these new approaches.

3. Canning, S., & Found, P. (2015). A review of the supporting literature for the ‘sustain’ step of the 7-step lean service improvement model. International Journal of Quality and Service Sciences, 7(2/3), 235-254. https://doi.org/10.1108/IJQSS-02-2015-0023

This peer-reviewed article discusses mechanisms for sustaining improvements. It highlights the importance of performance management systems, stating, "The performance management system needs to be aligned to the new way of working... This includes setting appropriate targets and measures" (p. 243). This directly supports the action described in Option B.