CCMP practice question 24 of 25
After communication meetings with all employees impacted by a change initiative, the feedback was that many of them do not understand the reasons for this change. Which part of the communications strategy is most likely to be revised to achieve desired outcome of change communication?
Full set: 150 questionsThe feedback explicitly states that employees "do not understand the reasons for this change." The business rationale, also known as the case for change, is the fundamental component of a change management and communication strategy that articulates the "why." It explains the drivers, justification, risks of not changing, and expected benefits. When stakeholders lack understanding of the reasons, it indicates a direct failure in the development or delivery of this core message. Therefore, revising the business rationale and how it is communicated is the most critical step to address the identified gap and build the necessary awareness and desire for the change.
B. Stakeholders should be able to change: This relates to ability, skills, and resources, which are addressed after stakeholders understand and accept the need for change.
C. Stakeholders should know how to change: This focuses on the "how" (e.g., training on new processes), which is irrelevant if the "why" is not understood first.
D. Stakeholders should be adaptable and focused on the future: This describes a desired cultural attribute or outcome, not a specific, actionable component of the communication strategy that explains the change's purpose.
1. The Standard for Change Management (Third Edition). Association of Change Management Professionals (ACMP), 2019.
Section 2.2, Develop the Change Management Strategy: This section notes that the strategy must define "key messages, including the case for change."
Section 3.3, Develop and Deliver Communication: This section specifies that communications must convey "the reason for the change and the alignment with the vision and business strategy." The feedback directly points to a failure in this area.
2. Hiatt, J. M. (2006). ADKAR: A model for change in business, government and our community. Prosci Learning Center Publications.
The "Awareness" phase of the ADKAR model, which is a foundational concept in change management, is built entirely on understanding the business reasons for change. The book states, "Awareness is the goal of the early phases of communications..." (Chapter 3). A lack of understanding of the reasons signifies a failure to build Awareness.
3. Cameron, E., & Green, M. (2019). Making Sense of Change Management: A Complete Guide to the Models, Tools and Techniques of Organizational Change (5th ed.). Kogan Page Publishers.
Chapter 6, "Communicating Change": This chapter emphasizes that the first and most crucial communication task is to create a compelling "change story" or "case for change" that answers the fundamental question of "Why is this change necessary?" for all stakeholders.
Keep practicing
Take the free CCMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCMP practice questions
- Question 1What is the main purpose of assessing how well new change initiatives are aligned to the …
- Question 2What is the most significant element to look for when conducting an assessment of an orga…
- Question 3What document should provide guidance and best practices for future change initiatives?
- Question 4What is a recommended practice for aligning stakeholders around benefits and value of a c…
- Question 5What could be a significant input to the analysis of change objectives and in defining ne…
- Question 6The first two weeks of a large and complex change project is underway and things seem to …