CCMP practice question 25 of 25
What process identifies those affected by the change and those with the ability to influence the outcome?
Full set: 150 questionsStakeholder analysis is a foundational process in change management used to systematically identify all individuals, groups, or organizations that can be affected by a change or can influence its success. The process involves assessing their interests, expectations, and level of influence. This information is crucial for developing effective communication and engagement strategies tailored to different stakeholder groups, thereby managing resistance and building support for the change initiative. This directly aligns with the question's description of identifying those affected and those with influence.
A. Competency assessment: This evaluates the skills and knowledge of individuals against required capabilities, not their relationship to or influence over a specific change.
C. Sponsor assessment: This is a focused evaluation of the change sponsor's commitment and effectiveness, representing only one component of a broader stakeholder analysis.
D. Learning needs analysis: This identifies training gaps for those impacted by the change to ensure they have the necessary skills post-implementation, a subsequent step to stakeholder identification.
1. Association of Change Management Professionals (ACMP). (2019). The Standard for Change Management.
Section 2.3, "Define the Change Management Strategy," outlines the necessity of stakeholder analysis. It specifies that this process identifies "individuals and groups who will be affected by the change and all those who have the ability to influence the outcome" as a prerequisite for developing the stakeholder engagement strategy (p. 18).
2. Cameron, E., & Green, M. (2019). Making Sense of Change Management: A Complete Guide to the Models, Tools and Techniques of Organizational Change (5th ed.). Kogan Page.
Chapter 7, "Stakeholder Engagement," describes stakeholder analysis as the process of identifying stakeholders and understanding their positions and influence regarding the change. It emphasizes mapping stakeholders based on their power and interest to manage their engagement effectively (pp. 155-158).
3. Project Management Institute (PMI). (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.).
Section 13.1, "Identify Stakeholders," defines this process as "identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success" (p. 507). This foundational concept is integral to change management practice.
Keep practicing
Take the free CCMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCMP practice questions
- Question 1What is the main purpose of assessing how well new change initiatives are aligned to the …
- Question 2What is the most significant element to look for when conducting an assessment of an orga…
- Question 3What document should provide guidance and best practices for future change initiatives?
- Question 4What is a recommended practice for aligning stakeholders around benefits and value of a c…
- Question 5What could be a significant input to the analysis of change objectives and in defining ne…
- Question 6The first two weeks of a large and complex change project is underway and things seem to …