CCMP practice question 14 of 25

What are the final steps to formally close a change effort?

Full set: 150 questions
Answer options
A: Review outcomes, complete business summary reviews, transfer ownership
B: Review outcomes, update change management plan, gain completion approval
C: Gain completion approval, transfer ownership, release resources Correct answer
D: Complete final summary report, transfer ownership, execute sustainability plan
Correct Answer:
C. Gain completion approval, transfer ownership, release resources
Explanation

The final steps to formally close a change effort involve a structured hand-off from the dedicated change management team to operational business units. According to the ACMP Standard for Change Management, the "Complete the Change Management Effort" process group includes obtaining final approval of outcomes, transferring ownership for ongoing activities, and releasing change management resources. This sequence ensures the change is formally accepted, its long-term sustainability is assigned to the appropriate owners, and the project-specific resources are officially demobilized, marking the definitive conclusion of the change initiative.

Why Incorrect

A. "Complete business summary reviews" is part of the post-project review process, which typically occurs after formal approval and resource release have been finalized.
B. Updating the change management plan is an iterative activity performed during the execution phase, not a final step in closing the effort.
D. Executing the sustainability plan is an ongoing operational responsibility that is transferred to the business, not a final closing task for the change team itself.

References

1. Association of Change Management Professionals (ACMP). (2019). The Standard for Change Management (Third Ed.).

Section 5.0, "Complete the Change Management Effort," pp. 21-22. This section outlines the key processes for closing a change effort. The tasks listed directly correspond to the elements in the correct answer:

5.1 Obtain Final Approval of Outcomes: This aligns with "Gain completion approval."

5.2 Transfer Ownership of Ongoing Change Management Activities: This aligns with "Transfer ownership."

5.3 Release Change Management Resources: This aligns with "Release resources."

2. Cameron, E., & Green, M. (2019). Making Sense of Change Management: A Complete Guide to the Models, Tools and Techniques of Organizational Change (5th ed.). Kogan Page.

Chapter 12, "Sustaining Change." This chapter discusses the importance of a structured handover process to ensure change is embedded. It emphasizes that formal closure includes transferring responsibility for monitoring and sustaining the change to line management and decommissioning the project team, which supports the concepts of transferring ownership and releasing resources.

3. MIT OpenCourseWare. (2012). 1.040 Project Management, Lecture 21: Project Closeout. Massachusetts Institute of Technology.

Slide 4, "Project Closeout Activities." This university courseware outlines project closure activities that parallel the ACMP Standard. Key activities listed include "Obtain client acceptance" (Gain approval), "Handover of project" (Transfer ownership), and "Demobilize team" (Release resources), confirming this sequence as a standard practice in formal project closure.