CCP practice question 4 of 25
What is a basic element of work or a task that must be performed over a given period of time in order to complete a project called?
Full set: 189 questionsAn activity is the fundamental, lowest-level element of work in a project schedule. It represents a specific task that must be performed over a defined period, consuming resources and incurring costs to contribute to the completion of a project deliverable. The Work Breakdown Structure (WBS) defines the deliverables (the "what"), while activities define the work required to create those deliverables (the "how"). This term precisely matches the question's description of a basic work element or task with a duration.
A. WBS element: A WBS element represents a deliverable or a component of the project's scope, not the specific action or task performed to create it.
C. Resource: A resource (e.g., labor, equipment, materials) is what is consumed to perform an activity, not the activity itself.
D. Commodity: A commodity is a type of bulk material or resource (e.g., concrete, steel) used in the project, not a task or element of work.
1. AACE International. (2022). Recommended Practice No. 10S-90: Cost Engineering Terminology. Morgantown, WV: AACE International.
Definition of Activity: "An element of work, task, or process that must be performed in order to complete a project. An activity has an expected duration, a cost, and resource requirements. In project management, an activity is the lowest level of detail in a project plan (e.g., a schedule or network logic diagram)."
2. Amos, S. J. (Ed.). (2012). Skills & Knowledge of Cost Engineering (6th ed.). AACE International.
Section 7.2.2, Activity Definition (p. 7.4): "An activity is a discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the project work. Activities are the basic building blocks of a project schedule."
3. Hegazy, T. (2002). Computer-Based Construction Project Management. University of Waterloo.
Chapter 3, Planning and Scheduling (p. 34): "The first step in preparing a project schedule is to break down the project into a number of manageable activities. An activity, or task, is a specific work element that consumes time and resources and has an identifiable start and end."
Keep practicing
Take the free CCP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCP practice questions
- Question 1A used concrete pumping truck can be purchased for $125,000. The operation costs are expe…
- Question 3Which of the following best describes the concept of total cost management:
- Question 5The goal of listening is to:
- Question 7When a person hears the words being said to him/her, but does not receive the message of …
- Question 8AACE International defines _____________as a technique of economic evaluation that sums o…
- Question 10_____________is defined as the budget for the cost (work) account times the percent compl…
