CDCS practice question 18 of 25
Do you need to consider blast protection when designing a data center?
Full set: 120 questionsThe decision to implement blast protection is a direct outcome of a thorough risk assessment, a fundamental step in data center design. This assessment must evaluate the specific threats to the facility. If the data center is identified as a potential target itself (e.g., a government or major financial institution) or is located in close proximity to other high-profile targets (e.g., embassies, major transport hubs, or critical infrastructure), the risk of being affected by an explosion is significant. In such scenarios, considering and likely implementing blast protection measures is a critical aspect of ensuring the physical security, resilience, and operational continuity of the data center.
A. The potential for an event, even if unpredictable, is precisely why risk assessments and mitigation strategies like blast protection are considered and implemented.
C. While ANSI/TIA-942 does not universally mandate blast protection, it requires a risk assessment that would necessitate considering it if the location or nature of the facility warrants it.
D. ANSI/TIA-942 does not make blast protection a mandatory requirement for all data centers; its implementation is based on a site-specific risk analysis.
1. ANSI/TIA-942-B, Telecommunications Infrastructure Standard for Data Centers.
Section 5.2, "Site Selection": This section details the requirement to evaluate risks associated with a potential site. It specifically mentions assessing proximity to man-made hazards, which includes potential targets for malicious acts.
Annex G, "Data center site selection and design considerations": This informative annex provides guidance on evaluating risks from man-made disasters, stating that "The data center should not be located in a high-risk area that is a likely target for man-made disasters." This directly supports the principle of considering threats based on location.
2. Uptime Institute, "Tier Standard: Topology"
Section: Site Selection: The standard mandates that "The site selection process shall include a risk assessment of the proposed location... Man-made disasters, both accidental and intentional, shall be evaluated." This reinforces that the decision is risk-based and contingent on the threat profile of the location, as described in option B.
3. Federal Emergency Management Agency (FEMA), "FEMA 426: Reference Manual to Mitigate Potential Terrorist Attacks Against Buildings"
Chapter 3, "Explosive Blast": This document provides detailed guidance on assessing blast threats and designing protective measures. It emphasizes that the level of protection is determined by a threat and vulnerability assessment, which considers whether a building is a likely target due to its function, symbolism, or proximity to other targets. This is an official source outlining the standard methodology for critical infrastructure protection.
Keep practicing
Take the free CDCS practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CDCS practice questions
- Question 1What mainly affects the cooling capacity of a raised floor tile?
- Question 2What is a potential disadvantage of using a hypoxic-based fire suppression system as a fi…
- Question 3The location of a data center is just above the Arctic Circle (North Pole). The outside a…
- Question 4A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lb…
- Question 5When installing a raised floor, can we use a spirit level bar to level the floor?
- Question 6The computer room has high levels of H2S gas contamination. What is the best option to re…