What are the four methods a project manager should use to prove project requirements are met?
Full set: 251 questionsThe four standard and widely accepted methods for verifying that project requirements have been met are Analysis, Inspection, Demonstration, and Testing. Option B is the best choice as it includes three of these four core methods: testing, analysis, and inspection. "Interpolation," while not a standard verification method itself, is a mathematical technique that could be used within the 'Analysis' method. The other options incorrectly mix verification methods with project management phases, administrative tasks, or communication techniques that are not primary methods for proving requirement fulfillment.
A. Planning, specifying, negotiating, and payment: These are distinct project management activities or phases, not methods used to verify that requirements have been met.
C. Interviewing, observing, inspecting, and reporting: This option incorrectly includes communication (interviewing) and documentation (reporting) as primary verification methods.
D. Analysis, reporting,measurement, and permit sign-off: This option incorrectly includes administrative outcomes (reporting, permit sign-off) which result from verification, rather than being the verification methods themselves.
1. NASA Systems Engineering Handbook (NASA/SP-2016-6105 Rev2): In Section 6.7, "Verification and Validation," the handbook explicitly states, "The four basic verification methods are inspection, analysis, demonstration, and test." This source provides the foundational model for technical requirement verification. (Page 161).
2. Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition: In Section 8.3.2, "Control Quality: Tools and Techniques," the guide lists "Inspection" and "Testing/Product Evaluations" as key techniques. It also includes "Data analysis" as a technique, which directly supports three of the four methods listed in the correct answer.
3. IFMA, Facility Management Professional (FMP) Learning System, Project Management Module: The principles within this official IFMA training material align with the PMBOK® Guide. The module on "Define Projects" and "Manage and Oversee Projects" covers the verification of project deliverables through processes like commissioning (testing) and final inspections (punch lists) to ensure they meet the specified requirements.
Keep practicing
Take the free CFM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CFM practice questions
- Question 1What is a good reason to get the facilities engineers involved early in the planning of a…
- Question 2What is an industry standard quality program?
- Question 3As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi…
- Question 4What is the correct order for strategic facility planning?
- Question 5When are the laws of supply and demand relative to price?
- Question 6What is the most common method to accelerate the completion of a project?