CFM practice question 31 of 35

What are the four methods a project manager should use to prove project requirements are met?

Full set: 251 questions
Answer options
A: Planning, specifying, negotiating, and payment
B: Testing, analysis, inspection, and interpolation Correct answer
C: Interviewing, observing, inspecting, and reporting
D: Analysis, reporting, measurement, and permit sign-off
Correct Answer:
B. Testing, analysis, inspection, and interpolation
Explanation

The four standard and widely accepted methods for verifying that project requirements have been met are Analysis, Inspection, Demonstration, and Testing. Option B is the best choice as it includes three of these four core methods: testing, analysis, and inspection. "Interpolation," while not a standard verification method itself, is a mathematical technique that could be used within the 'Analysis' method. The other options incorrectly mix verification methods with project management phases, administrative tasks, or communication techniques that are not primary methods for proving requirement fulfillment.

Why Incorrect

A. Planning, specifying, negotiating, and payment: These are distinct project management activities or phases, not methods used to verify that requirements have been met.
C. Interviewing, observing, inspecting, and reporting: This option incorrectly includes communication (interviewing) and documentation (reporting) as primary verification methods.
D. Analysis, reporting,measurement, and permit sign-off: This option incorrectly includes administrative outcomes (reporting, permit sign-off) which result from verification, rather than being the verification methods themselves.

References

1. NASA Systems Engineering Handbook (NASA/SP-2016-6105 Rev2): In Section 6.7, "Verification and Validation," the handbook explicitly states, "The four basic verification methods are inspection, analysis, demonstration, and test." This source provides the foundational model for technical requirement verification. (Page 161).

2. Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition: In Section 8.3.2, "Control Quality: Tools and Techniques," the guide lists "Inspection" and "Testing/Product Evaluations" as key techniques. It also includes "Data analysis" as a technique, which directly supports three of the four methods listed in the correct answer.

3. IFMA, Facility Management Professional (FMP) Learning System, Project Management Module: The principles within this official IFMA training material align with the PMBOK® Guide. The module on "Define Projects" and "Manage and Oversee Projects" covers the verification of project deliverables through processes like commissioning (testing) and final inspections (punch lists) to ensure they meet the specified requirements.

Scroll to Top