CFM practice question 6 of 35

What is the most common method to accelerate the completion of a project?

Full set: 251 questions
Answer options
A: Outsourcing project work
B: Reducing scope
C: Adding resources Correct answer
D: Scheduling overtime
Correct Answer:
C. Adding resources
Explanation

The most common and direct method to accelerate a project's completion is known as "crashing." This schedule compression technique involves adding resources—such as more personnel, specialized equipment, or additional funding—to activities on the project's critical path. The goal is to shorten the duration of these key activities, thereby reducing the overall project timeline. While this approach typically increases the project's direct costs, it is a standard and widely applied strategy when meeting a deadline is a higher priority than minimizing cost, without changing the project's scope.

Why Incorrect

A. Outsourcing project work: This is a procurement strategy that may or may not accelerate the project; it is often chosen for cost, expertise, or capacity reasons, not solely for speed.
B. Reducing scope: This fundamentally changes the project's deliverables. It is a method to finish earlier by delivering less, not a method to accelerate the completion of the original work.
D. Scheduling overtime: This is a specific tactic of adding resources (labor hours). However, it is a subset of the broader "adding resources" strategy and can lead to diminished productivity and burnout.

References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 6.6.2.4, "Schedule Compression." This section defines crashing as a technique to shorten schedule duration by adding resources and notes it is used when schedule compression is needed.

2. Meredith, J. R., Shafer, S. M., & Mantel Jr., S. J. (2017). Project Management: A Managerial Approach (10th ed.). Wiley. In Chapter 8, "Scheduling," the text describes crashing as a primary method for shortening project time by applying additional resources to critical path activities.

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). John Wiley & Sons. Chapter 17, "Time/Cost Trade-off," details crashing as a primary technique for schedule compression, which involves the allocation of more resources to shorten activity durations.