CFM practice question 7 of 35

A facility manager may be responsible for status reviews on projects. Why are status reviews important and valuable?

Full set: 251 questions
Answer options
A: To identify reasons for variance from baseline and ensure responsible parties are identified
B: To keep accurate records of all project tasks regardless of variation from baseline
C: To identify issues and corrective actions to ensure the project remains on track Correct answer
D: To keep the project team aware of others’ progress on a project
Correct Answer:
C. To identify issues and corrective actions to ensure the project remains on track
Explanation

Project status reviews are a core component of the project monitoring and control process. Their primary value is to provide a regular, structured forum for assessing project performance against the established baseline (scope, schedule, and budget). The main purpose is to proactively identify risks, issues, and deviations from the plan. By identifying these problems early, the project team and stakeholders can develop and implement timely corrective actions to bring the project back on track and ensure it successfully meets its objectives. This forward-looking, problem-solving approach is the key value of the review process.

Why Incorrect

A. The primary goal is collaborative problem-solving to correct variance, not to assign blame, which can be detrimental to team morale and project success.
B. Accurate record-keeping is a function of project administration and an outcome of the review, but the review's main purpose is active management and control, not passive documentation.
D. While status reviews do enhance team awareness, this is a secondary benefit. The primary objective is active project control and decision-making to resolve issues.

References

1. IFMA, The Facility Management Body of Knowledge (FM BOK), Project Management competency area. The BOK emphasizes that project management involves "monitoring and controlling" activities. Status reviews are a key tool for this, enabling the facility manager to "track project progress and performance, identify variances, and take corrective actions as needed." This directly aligns with identifying issues and implementing corrective actions to keep the project on track. (Specific section: Project Management > Monitoring and Controlling Process Group).

2. Hodges, C. B. (2015). Project Management for Facility Managers. Association of University Directors of Estates (AUDE). This university-affiliated guide states, "The purpose of a progress meeting [status review] is to review progress against the programme, identify any current or potential problems and agree the actions to be taken... It is a key project control tool." (Chapter 10: Project Control, Section on Progress Meetings, p. 112).

3. El-Sayegh, S. M., & Mansour, M. H. (2015). Risk assessment and allocation in highway construction projects in the UAE. Journal of Management in Engineering, 31(6), 04015004. While focused on construction, this peer-reviewed article discusses project control mechanisms, noting that regular project reviews are essential for "early identification of problems and implementation of corrective actions" to mitigate risks and prevent project failure. This supports the idea that the primary function is proactive issue identification and correction. (DOI: https://doi.org/10.1061/(ASCE)ME.1943-5479.0000365, Section: Risk Monitoring and Control).