CFM practice question 7 of 35
A facility manager may be responsible for status reviews on projects. Why are status reviews important and valuable?
Full set: 251 questionsProject status reviews are a core component of the project monitoring and control process. Their primary value is to provide a regular, structured forum for assessing project performance against the established baseline (scope, schedule, and budget). The main purpose is to proactively identify risks, issues, and deviations from the plan. By identifying these problems early, the project team and stakeholders can develop and implement timely corrective actions to bring the project back on track and ensure it successfully meets its objectives. This forward-looking, problem-solving approach is the key value of the review process.
A. The primary goal is collaborative problem-solving to correct variance, not to assign blame, which can be detrimental to team morale and project success.
B. Accurate record-keeping is a function of project administration and an outcome of the review, but the review's main purpose is active management and control, not passive documentation.
D. While status reviews do enhance team awareness, this is a secondary benefit. The primary objective is active project control and decision-making to resolve issues.
1. IFMA, The Facility Management Body of Knowledge (FM BOK), Project Management competency area. The BOK emphasizes that project management involves "monitoring and controlling" activities. Status reviews are a key tool for this, enabling the facility manager to "track project progress and performance, identify variances, and take corrective actions as needed." This directly aligns with identifying issues and implementing corrective actions to keep the project on track. (Specific section: Project Management > Monitoring and Controlling Process Group).
2. Hodges, C. B. (2015). Project Management for Facility Managers. Association of University Directors of Estates (AUDE). This university-affiliated guide states, "The purpose of a progress meeting [status review] is to review progress against the programme, identify any current or potential problems and agree the actions to be taken... It is a key project control tool." (Chapter 10: Project Control, Section on Progress Meetings, p. 112).
3. El-Sayegh, S. M., & Mansour, M. H. (2015). Risk assessment and allocation in highway construction projects in the UAE. Journal of Management in Engineering, 31(6), 04015004. While focused on construction, this peer-reviewed article discusses project control mechanisms, noting that regular project reviews are essential for "early identification of problems and implementation of corrective actions" to mitigate risks and prevent project failure. This supports the idea that the primary function is proactive issue identification and correction. (DOI: https://doi.org/10.1061/(ASCE)ME.1943-5479.0000365, Section: Risk Monitoring and Control).
Keep practicing
Take the free CFM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CFM practice questions
- Question 1What is a good reason to get the facilities engineers involved early in the planning of a…
- Question 2What is an industry standard quality program?
- Question 3As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi…
- Question 4What is the correct order for strategic facility planning?
- Question 5When are the laws of supply and demand relative to price?
- Question 6What is the most common method to accelerate the completion of a project?