CFM practice question 8 of 35

In relation to establishing a level of acceptable risk, what should you include in your Business Continuity Plan (BCP) to help measure the plan's expected level of success against that level of risk?

Full set: 251 questions
Answer options
A: Contracted support
B: Lessons learned
C: Business analysis
D: Performance metrics Correct answer
Correct Answer:
D. Performance metrics
Explanation

Performance metrics are the tools used to measure the success of a Business Continuity Plan (BCP) against the organization's established level of acceptable risk. These metrics, such as Recovery Time Objectives (RTOs) and Recovery Point Objectives (RPOs), are defined during the business impact analysis phase and are integrated into the BCP. They provide specific, quantifiable targets that allow the organization to assess whether critical business functions are restored within the required timeframes and with an acceptable level of data loss. During tests, exercises, or an actual event, performance against these metrics directly indicates the plan's effectiveness and its alignment with the organization's risk tolerance.

Why Incorrect

A. Contracted support: This is a recovery strategy or resource used to execute the plan, not a tool for measuring its success.
B. Lessons learned: This is a qualitative outcome of a post-event review used for future improvement, not the pre-defined measure of success.
C. Business analysis: This is a foundational activity (e.g., Business Impact Analysis) that defines the requirements for the BCP, rather than measuring its performance.

References

1. ISO 22301:2019, Security and resilience — Business continuity management systems — Requirements. Clause 9.1, "Monitoring, measurement, analysis and evaluation," explicitly states that the organization shall determine what needs to be monitored and measured, and the methods for doing so, to evaluate the business continuity performance and the effectiveness of the business continuity management system (BCMS). This directly supports the use of performance metrics.

2. Roper, K. O., & Payant, R. P. (2014). The Facility Management Handbook (4th ed.). AMACOM. Chapter 21, "Emergency Preparedness and Business Continuity," details the BCP lifecycle. It emphasizes that testing and exercising the plan are critical for validating its effectiveness. This validation is performed by measuring the outcome against pre-defined objectives (RTOs/RPOs), which function as the core performance metrics.

3. Carli, C. (2010). Measuring Operational Resilience (CMU/SEI-2010-TN-026). Carnegie Mellon University, Software Engineering Institute. This technical note discusses the necessity of metrics for managing and measuring resilience. It states, "Measurement provides the basis for organizations to assess the current state of their operational resilience management capability... and determine whether they are meeting their performance targets" (p. 1). This reinforces the principle of using metrics to evaluate performance against established goals.