CFM practice question 9 of 35
Both the facility and information technology managers are asked to assign staff to work together on a major project. Halfway through the project, the managers observe that the team is in a win-lose power struggle because of divergent views among team members. How should the facility and information technology managers initially intervene?
Full set: 251 questionsThe team is experiencing a "win-lose power struggle," which is characteristic of the "storming" phase of team development. The most effective and appropriate initial intervention by management is to impose structure and clarify processes. Reestablishing meeting guidelines, communication protocols, and decision-making rules directly addresses the procedural breakdown causing the conflict. This approach facilitates a move from conflict to collaboration by creating a clear, agreed-upon framework for the team to manage their divergent views constructively, without resorting to disruptive changes in personnel or team structure.
B. Reassign project managers: This is a drastic and disruptive action, not an initial step. It should only be considered if process-based interventions fail and leadership is proven to be the core problem.
C. Assign new team members who have similar personalities: This avoids addressing the root cause, which is a lack of process for managing conflict. It is also poor management practice to build teams based on personality similarity, as this can stifle diversity of thought.
D. Assign additional members from each department to foster more problem-solving: Adding more people to a team already in conflict will likely increase complexity and escalate the power struggle rather than resolve it.
1. IFMA. (2020). IFMA's Core Competencies. In the Leadership and Strategy competency, the topic of "Manage/oversee the work of the facility management team" emphasizes the manager's role in establishing clear expectations, managing conflict, and facilitating team processes. The initial response to conflict is to reinforce or create structure, not to change personnel.
2. Roper, K. O., & Payant, R. P. (2014). The Facility Management Handbook (4th ed.). AMACOM. Chapter 5, "Leadership, Management, and Role of the Facility Manager," outlines the manager's responsibility to guide teams. This includes establishing operating procedures and ground rules to manage team dynamics and resolve conflicts effectively, which aligns with reestablishing guidelines as a primary intervention.
3. Tuckman, B. W. (1965). Developmental sequence in small groups. Psychological Bulletin, 63(6), 384–399. This foundational academic paper introduces the "forming, storming, norming, performing" model. The "storming" stage (p. 386) is defined by intragroup conflict. The resolution of this stage involves the development of group norms and structure, which is precisely what reestablishing guidelines aims to achieve. (DOI: https://doi.org/10.1037/h0022100)
Keep practicing
Take the free CFM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CFM practice questions
- Question 1What is a good reason to get the facilities engineers involved early in the planning of a…
- Question 2What is an industry standard quality program?
- Question 3As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi…
- Question 4What is the correct order for strategic facility planning?
- Question 5When are the laws of supply and demand relative to price?
- Question 6What is the most common method to accelerate the completion of a project?