CFM practice question 10 of 35
Departments often forget to budget for equipment design and installation costs. What is the best solution?
Full set: 251 questionsThe most effective and strategic solution is to integrate the Facilities department into the capital budgeting process from the outset. Establishing a formal procedure for Facilities to provide input ensures that expert knowledge on design, installation, infrastructure impact, and associated costs is included in departmental budgets before they are finalized. This proactive approach prevents budget shortfalls, aligns facility requirements with departmental needs, and supports accurate financial planning and control for the entire organization. It addresses the root cause of the problem—a lack of information and coordination during the planning phase.
A. Develop a procedure that would charge back capital installation costs to the department procuring the equipment. This is a reactive accounting measure, not a budgeting solution. It doesn't prevent the initial budget omission and can create financial strain on departments that did not plan for the expense.
B. Mark up each equipment capital request by 15% to cover design and installation costs. This is an arbitrary, "one-size-fits-all" approach. A fixed percentage is unlikely to accurately reflect the true costs, which can vary significantly depending on the complexity of the equipment and installation.
D. Create a facilities installation fund that is 15% of the company’s annual capital equipment fund to cover these costs. This method also relies on an arbitrary percentage and disconnects the installation costs from the specific project and department, reducing accountability and the accuracy of project-specific budgeting.
1. IFMA. (2021). The Facility Management Handbook (4th ed.). Chapter 10, "Financial Management," emphasizes the facility manager's role in developing accurate budgets and participating in the organization's capital budgeting process. It states, "The facility manager must be involved in the organization’s capital budgeting process to ensure that facility projects are properly funded" (p. 215). This supports integrating FM input (Option C) over reactive or arbitrary methods.
2. Cotts, D. G., Roper, K. A., & Payant, R. P. (2010). The Facility Management Handbook (3rd ed.). AMACOM. In Chapter 20, "Capital Project Management," the authors detail the importance of the planning and programming phase, which includes developing a comprehensive project budget. The text underscores that accurate cost estimating, which requires input from the facility management team, is critical in the early stages to secure appropriate funding. This aligns directly with the proactive approach in Option C.
3. Hodges, C. B. (2016). Managing the built environment in healthcare. Routledge. While focused on healthcare, the principles are broadly applicable. Chapter 5, "Financial Management and Budgeting," discusses the necessity of including all project-related costs in capital requests. It highlights that "failure to account for enabling costs, such as utility upgrades or structural modifications [i.e., installation costs], is a common cause of budget overruns." The solution presented is a rigorous, integrated review process involving the facilities department, as described in Option C. (DOI: https://doi.org/10.4324/9781315756589)
Keep practicing
Take the free CFM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CFM practice questions
- Question 1What is a good reason to get the facilities engineers involved early in the planning of a…
- Question 2What is an industry standard quality program?
- Question 3As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi…
- Question 4What is the correct order for strategic facility planning?
- Question 5When are the laws of supply and demand relative to price?
- Question 6What is the most common method to accelerate the completion of a project?