CFM practice question 11 of 35
What steps should be taken to create a risk assessment and risk plan?
Full set: 251 questionsThe creation of a risk assessment and risk plan follows a structured, universally accepted process. The initial step is to systematically identify all potential risks that could affect the project or facility operations. Following identification, each risk is analyzed through a risk assessment to determine its probability of occurrence and the severity of its potential impact. This analysis allows for prioritization. Finally, a risk plan is developed, which outlines specific strategies, such as contingency plans, to mitigate, transfer, avoid, or accept each prioritized risk, thereby preparing the organization to manage them effectively.
B. Communicating risks and requesting funds are subsequent actions taken after the core assessment and plan have been developed, not the foundational steps for creating them.
C. Adding cushions (buffers) and identifying scope to be cut are specific risk response strategies, which are part of the final plan, not the entire creation process.
D. Project management tools like PERT or Gantt charts are used to support the risk management process, but they are not the process steps themselves.
1. IFMA. (n.d.). Project Management Competency. In the IFMA framework, the Project Management competency requires facility managers to "develop and manage/oversee project management plans (e.g., scope, schedule, budget, risk, quality, etc.)." The standard methodology for risk planning involves the sequence of identification, analysis (probability/impact), and response planning, as outlined in option A.
2. Roper, K. O., & Payant, R. P. (2014). The Facility Management Handbook (4th ed.). AMACOM. Chapter 21, "Managing Projects," describes the project management life cycle. Within this, risk management is detailed as a process of "identifying, analyzing, and responding to project risk" (p. 387), which directly supports the steps of identification, determining probability/severity, and developing plans.
3. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Chapter 11, "Project Risk Management," formally defines the process. The key process groups are: 11.2 Identify Risks, 11.3 Perform Qualitative Risk Analysis (which assesses probability and impact), and 11.5 Plan Risk Responses (which includes developing contingency plans). This industry-standard framework, widely adopted in facility management, validates the sequence in option A.
Keep practicing
Take the free CFM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CFM practice questions
- Question 1What is a good reason to get the facilities engineers involved early in the planning of a…
- Question 2What is an industry standard quality program?
- Question 3As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi…
- Question 4What is the correct order for strategic facility planning?
- Question 5When are the laws of supply and demand relative to price?
- Question 6What is the most common method to accelerate the completion of a project?