What steps should be taken to create a risk assessment and risk plan?

Full set: 251 questions
Answer options
A: Identify the risks. Determine the probability and severity of each risk. Develop contingency plans to ameliorate each risk. Correct answer
B: Communicate the risks to stakeholders. Request additional funds to cover contingencies on the most important risks.
C: Add additional days to activity durations to build in a cushion. Identify areas in the project that can be cut out, if necessary.
D: Utilize project tools. PERT or Gantt charts, work breakdown structures to identify risk, track issues, and mitigation risks.
Correct Answer:
A. Identify the risks. Determine the probability and severity of each risk. Develop contingency plans to ameliorate each risk.
Explanation

The creation of a risk assessment and risk plan follows a structured, universally accepted process. The initial step is to systematically identify all potential risks that could affect the project or facility operations. Following identification, each risk is analyzed through a risk assessment to determine its probability of occurrence and the severity of its potential impact. This analysis allows for prioritization. Finally, a risk plan is developed, which outlines specific strategies, such as contingency plans, to mitigate, transfer, avoid, or accept each prioritized risk, thereby preparing the organization to manage them effectively.

Why Incorrect

B. Communicating risks and requesting funds are subsequent actions taken after the core assessment and plan have been developed, not the foundational steps for creating them.
C. Adding cushions (buffers) and identifying scope to be cut are specific risk response strategies, which are part of the final plan, not the entire creation process.
D. Project management tools like PERT or Gantt charts are used to support the risk management process, but they are not the process steps themselves.

References

1. IFMA. (n.d.). Project Management Competency. In the IFMA framework, the Project Management competency requires facility managers to "develop and manage/oversee project management plans (e.g., scope, schedule, budget, risk, quality, etc.)." The standard methodology for risk planning involves the sequence of identification, analysis (probability/impact), and response planning, as outlined in option A.

2. Roper, K. O., & Payant, R. P. (2014). The Facility Management Handbook (4th ed.). AMACOM. Chapter 21, "Managing Projects," describes the project management life cycle. Within this, risk management is detailed as a process of "identifying, analyzing, and responding to project risk" (p. 387), which directly supports the steps of identification, determining probability/severity, and developing plans.

3. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Chapter 11, "Project Risk Management," formally defines the process. The key process groups are: 11.2 Identify Risks, 11.3 Perform Qualitative Risk Analysis (which assesses probability and impact), and 11.5 Plan Risk Responses (which includes developing contingency plans). This industry-standard framework, widely adopted in facility management, validates the sequence in option A.