What do as-built drawings document?
Full set: 251 questionsAs-built drawings, often referred to as record drawings, are a revised set of drawings submitted by a contractor upon completion of a project. They reflect all changes made during the construction process that deviate from the original construction documents. These drawings document the exact dimensions, geometry, and location of all elements of the work as constructed in the field. This provides the facility manager with an accurate record of the building and its systems, which is essential for future operations, maintenance, and renovation projects.
A. A construction drawing bid set is the package of documents issued to contractors before construction to solicit pricing and bids.
B. Architectural drawings after design development are an intermediate step in the design phase, occurring before the final construction documents are created.
D. A space program is a planning document that outlines functional and spatial needs before the design process even begins.
1. Roper, K. O., & Payant, R. P. (2014). The Facility Management Handbook (4th ed.). AMACOM. In Chapter 11, "Project Management," the text describes project closeout activities, which include the contractor providing "as-built drawings showing how the facility was actually constructed versus how it was designed" (p. 269).
2. American Institute of Architects (AIA). (2017). The Architect's Handbook of Professional Practice (15th ed.). Wiley. Chapter 10, "Construction Contract Administration," Section 10.5, "Project Closeout," details the contractor's responsibility to submit "record drawings" that show a record of the changes made during construction.
3. Sears, S. K., Sears, G. A., Clough, R. H., & Rounds, J. L. (2015). Construction Project Management: A Practical Guide to Field Construction Management (6th ed.). Wiley. Chapter 17, "Project Closeout," explains that as-built drawings are "marked-up prints showing 'as-built' changes" and are crucial for the owner's future use of the facility (p. 451).
Keep practicing
Take the free CFM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CFM practice questions
- Question 1What is a good reason to get the facilities engineers involved early in the planning of a…
- Question 2What is an industry standard quality program?
- Question 3As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi…
- Question 4What is the correct order for strategic facility planning?
- Question 5When are the laws of supply and demand relative to price?
- Question 6What is the most common method to accelerate the completion of a project?