There are several techniques that can be used when planning a project. Which of the following best describes a Work Breakdown Structure?

Full set: 210 questions
Answer options
A: A technique which can be used with critical path analysis to deal with uncertainties and risk within the project.
B: A set of documents identifying each stage and task to be performed during development, defining a hierarchy of work prior to the allocation of tasks. Correct answer
C: A method of scheduling tasks using a chart on which bars represents the relative length of the task.
D: A technique to arrange activities required to achieve the project objective, agreeing the objectives and determining exactly  the project aims.
Correct Answer:
B. A set of documents identifying each stage and task to be performed during development, defining a hierarchy of work prior to the allocation of tasks.
Explanation

A Work Breakdown Structure (WBS) is a fundamental project management tool used for defining and organizing the total scope of a project. It is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team. The WBS visually subdivides the project scope into smaller, more manageable components, such as phases, deliverables, and work packages. This hierarchical structure provides a clear framework for planning, scheduling, cost estimating, and assigning responsibilities, ensuring that all necessary work is identified before tasks are allocated.

Why Incorrect

A. This describes the Program Evaluation and Review Technique (PERT), which uses probabilistic time estimates to account for uncertainty, often in conjunction with critical path analysis.
C. This describes a Gantt chart, a bar chart that illustrates a project schedule, showing the start and finish dates of terminal elements and summary elements.
D. This describes the project initiation or scope definition phase, which is a broader process of establishing project goals, rather than the specific tool (WBS) used to break down the work.

References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 5.4, "Create WBS," defines the WBS as "a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables."

2. CIMA (2019). E2 Managing Performance, Study Text. Kaplan Publishing UK. Chapter 12, Section 2.2, "Work breakdown structure (WBS)," describes it as a tool that breaks a project down into a series of smaller tasks, creating a hierarchy.