CIS-PA practice question 9 of 15

Which property indicates the recommended evaluation date for a Target?

Full set: 60 questions
Answer options
A: Improvement Date
B: Baseline Date
C: End Date
D: Review Date Correct answer
Correct Answer:
D. Review Date
Explanation

The Target record form includes a 'Review date' field. This field is specifically designed to schedule a future date for the evaluation of the target's performance and progress. While the 'End date' marks the conclusion of the target period, the 'Review date' serves as a formal reminder or trigger for a performance assessment, making it the recommended evaluation date.

Why Incorrect

A. Improvement Date: This is not a standard field on the Target form in Performance Analytics.
B. Baseline Date: This date is the starting point from which improvement is measured, not the date for evaluation.
C. End Date: This is the date the target becomes inactive, but evaluation may be scheduled before or after this date.

References

- ServiceNow Product Documentation, "Create a target," Target form fields table. The documentation explicitly defines the 'Review date' field as the "Date on which you want to review the target."