A checklist item record provides a name and what other element?
Full set: 112 questionsDomain Agile and SAFe Management
A checklist item record (syschecklistitem) in ServiceNow is fundamentally composed of two key elements. The first is the name field, which is a string that holds the descriptive text for the to-do item. The second is the complete field, which is a boolean (True/False) data type. In the user interface, this complete field is rendered as a checkbox. When a user marks an item as done, the value of the complete field is set to true. This simple structure provides a clear, binary status for each item on the list.
A. Short description field: The name field itself serves as the description for the checklist item; a separate short description field is not a standard element on the record.
B. Status field: Checklist items track completion with a simple boolean complete field (done/not done), not a more complex, multi-state status field.
C. Percent complete field: This field is typically associated with larger work items like tasks or projects, not with individual, binary (complete/incomplete) checklist items.
1. ServiceNow Product Documentation - Checklists: The official documentation describes the functionality of checklists, stating, "Each item in the checklist has a check box that you can select to mark the item complete." This directly implies a completion field.
Source: ServiceNow Product Documentation, "Checklists," Vancouver Release.
2. ServiceNow Developer Documentation - Tables & Columns: An examination of the system dictionary for the syschecklistitem table confirms its structure. The table's default columns include name (Type: String) and complete (Type: True/False), which validates the correct answer.
Source: ServiceNow Developer Site, "Tables & Columns" module for the syschecklistitem table.
Keep practicing
Take the free CIS-SPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CIS-SPM practice questions
- Question 1At which point in the Demand Management lifecycle do assessments get sent to stakeholders?
- Question 2A program is a container for the following except for:
- Question 3In which table can you find cost information for a specific fiscal period?
- Question 4Which options are available in the' Effort type' field on the Resource Assignments form, …
- Question 5How can the latest financial forecasts (actuals or planned costs) be compared to initial …
- Question 6The combination of the user and the assigned portfolio must be unique when adding a user …