CIS-SPM practice question 8 of 25
If an it_project_manager does not want to equally distribute hours across the resource plan time frame, what allocation spread should be used?
Full set: 112 questionsDomain SPM Fundamentals
The question asks for an allocation spread to use when hours should not be distributed equally. ServiceNow Resource Management provides specific allocation types for resource plans. The 'Even' spread distributes hours equally across the plan's duration. To achieve an unequal distribution, the project manager must choose either 'Front Load,' which allocates more hours at the beginning of the plan, or 'Back Load,' which allocates more hours toward the end. Both options fulfill the stated requirement of not distributing hours equally.
A. Even: This option directly contradicts the requirement, as it is designed specifically to distribute hours equally over the time frame.
B. Any: This is not a valid, configurable allocation spread type within the ServiceNow platform. While conceptually the project manager could use "any" of the non-even methods, it is not a selectable option.
1. ServiceNow Product Documentation - Create a resource plan: "The allocation type for the resource plan.
Even load: Distributes the allocated hours evenly across the duration of the resource plan.
Front load: Allocates more hours at the beginning of the resource plan.
Back load: Allocates more hours at the end of the resource plan."
This documentation explicitly lists 'Front Load' and 'Back Load' as the methods for non-even distribution.
2. ServiceNow Product Documentation - Resource allocation: "You can allocate resources to a project or a demand by creating a resource plan. You can also modify the resource plan to change the allocation of resources... The allocation type for the resource plan: Even load, Front load, or Back load."
This confirms the specific, limited set of allocation types available, from which 'Front Load' and 'Back Load' are the only non-even options.
Keep practicing
Take the free CIS-SPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CIS-SPM practice questions
- Question 1At which point in the Demand Management lifecycle do assessments get sent to stakeholders?
- Question 2A program is a container for the following except for:
- Question 3In which table can you find cost information for a specific fiscal period?
- Question 4Which options are available in the' Effort type' field on the Resource Assignments form, …
- Question 5How can the latest financial forecasts (actuals or planned costs) be compared to initial …
- Question 6The combination of the user and the assigned portfolio must be unique when adding a user …