CIS-SPM practice question 24 of 25

Using the Request type field on a resource plan, which options can be used to request a resource? Choose 3 answers

Full set: 112 questions

Domain SPM Fundamentals

Answer options
A: Day
B: FTE Correct answer
C: Person Days Correct answer
D: Hours Correct answer
E: Month
Correct Answer:
B. FTE; C. Person Days; D. Hours
Explanation

The Request type field on a ServiceNow resource plan form specifies the unit of measurement for the resource request. The system provides three distinct options to cater to different planning methodologies. These options are Hours, which requests a specific total number of working hours; FTE (Full-Time Equivalent), which requests a percentage of a resource's total capacity; and Person Days, which requests a total number of full workdays. These choices offer flexibility for resource managers to align requests with project estimation techniques and organizational standards.

Why Incorrect

A. Day: This is not a valid option. The correct term for a daily unit of effort within ServiceNow resource plans is 'Person Days'.
E. Month: This is not a supported unit for the Request type field. Resource planning is done at a more granular level using Hours, FTE, or Person Days.

References

1. ServiceNow Product Documentation: Resource Management > Resource planning > Create a resource plan. In the table describing the fields on the Resource Plan form, the "Request type" field is explicitly defined with the choices: "Hours", "FTE", and "Person days". This document is the primary source for form field definitions in the platform.

2. ServiceNow Product Documentation: Resource Management > Resource planning > Resource plan states. This page, while discussing states, implicitly confirms the request types by describing how allocations are calculated based on Hours, FTE, or Person Days, reinforcing these as the core units of request.