CLSSGB-001 practice question 25 of 30

A Belt concludes a Lean Six Sigma project with the creation of a Control Plan. At what point can the Control Plan be closed?

Full set: 200 questions
Answer options
A: Never, a Control Plan is a living document Correct answer
B: As soon as the Champion signs off
C: Within 30 days of the LSS project review team meeting
D: After the project has been presented at the recognition event
Correct Answer:
A. Never, a Control Plan is a living document
Explanation

The Control Plan is a critical deliverable of the Control Phase in a DMAIC project, designed to ensure that the improvements are sustained over time. It is not a static project artifact but a "living document" that is handed over to the process owner. The process owner is responsible for using and updating the Control Plan whenever there are changes to the process, measurement systems, or specifications. Its purpose is to provide a written summary of the systems used to monitor and control the process, making its lifecycle tied to the process itself, not the project timeline.

Why Incorrect

B. As soon as the Champion signs off: The Champion's sign-off marks the formal closure of the Lean Six Sigma project, not the end of the control mechanisms. The plan is handed over for ongoing use at this point.
C. Within 30 days of the LSS project review team meeting: This suggests an arbitrary deadline. A review meeting might trigger an update to the plan, but it does not define the end of its useful life.
D. After the project has been presented at the recognition event: A recognition event is a communication and motivational tool. It has no procedural or technical bearing on the operational status of the process controls.

References

1. Automotive Industry Action Group (AIAG). (2008). Advanced Product Quality Planning and Control Plan (APQP) Second Edition. Section 6.2, Control Plan. The manual states, "The Control Plan is a living document and should be updated to reflect the addition or deletion of controls...". This is a foundational text for quality management systems and control planning.

2. Montgomery, D. C. (2013). Introduction to Statistical Quality Control (7th ed.). John Wiley & Sons. In Chapter 1, "Quality Improvement in the Modern Business Era," the text discusses the final phase of the DMAIC process, Control, emphasizing the need to "put a process monitoring and control system in place to make sure that the gains are permanent" (p. 21). This implies a continuous, not a time-bound, activity.

3. University of Michigan, College of Engineering. (n.d.). Lean Six Sigma Green Belt Certification Courseware. In the module on the Control Phase, the materials describe the Control Plan as a document transferred to the process owner for long-term management and continuous improvement, highlighting its role beyond the project's conclusion.

Scroll to Top