CPIM-MPR practice question 11 of 25

Translation of a master production schedule directly into key resources results in a:

Full set: 105 questions
Answer options
A: production schedule.
B: final assembly schedule.
C: rough-cut capacity plan. Correct answer
D: bill of labor.
Correct Answer:
C. rough-cut capacity plan.