CPIM-MPR practice question 10 of 25

The resource profile approach to rough-cut capacity planning is desirable in the manufacture of parts with lengthy lead times because the approach:

Full set: 105 questions
Answer options
A: uses detailed data about time standards for each product at the key resources.
B: assumes that all components are built in the same period as the end item.
C: considers the historical portion of the total plant time required.
D: time phases labor requirements. Correct answer
Correct Answer:
D. time phases labor requirements.