CPIM-MPR practice question 8 of 25

Which of the following statements is true about items that appear on a final assembly schedule?

Full set: 105 questions
Answer options
A: They do not appear on a shipment schedule.
B: They are stated in terms of end items or customer orders. Correct answer
C: They are released without regard for component availability.
D: They are used as input to the production plan.
Correct Answer:
B. They are stated in terms of end items or customer orders.