In a lean environment, one uses material requirements planning (MRP) processing primarily to:
Full set: 151 questionsIn a lean environment, one uses material requirements planning (MRP) processing primarily to create plans to share with suppliers. MRP is a software-based system that calculates the quantity and timing of materials needed for production, based on the master production schedule, the bill of materials, and the inventory status. MRP helps to coordinate the flow of materials from suppliers to the production process, reducing waste and inventory costs. MRP can also generate purchase orders, work orders, and other documents to communicate the plans with suppliers and internal departments. MRP does not calculate average daily demand, which is a measure of the average amount of a product or service that is sold or consumed per day. MRP does not determine the kanban circuit locations, which are the physical places where kanban cards or containers are exchanged between processes in a pull system. MRP does not determine where to use supermarkets, which are locations where a small amount of inventory is kept to buffer against fluctuations in demand or supply. Reference: CPIM Exam Content Manual Version 7.0, Domain 4: Plan and Manage Supply, Section 4.1: Supply Planning Concepts, p. 24; Lean MRP; Manufacturing resource planning.
Keep practicing
Take the free CPIM-PART-2 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CPIM-PART-2 practice questions
- Question 2Up-to-date information about production order status is required to do which of the follo…
- Question 3The results from responding to uncertainty in the supply chain by exaggerating lead times…
- Question 4The capacity requirements plan is used primarily to:
- Question 5Which of the following outcomes is a benefit of mixed-model scheduling?
- Question 6Which of the following tools is used to evaluate the impact that a production plan has on…
- Question 7The demonstrated capacity of equipment in a process flow is $1,200 per day. Due to a malf…