CPIM-PART-2 practice question 4 of 25
The capacity requirements plan is used primarily to:
Full set: 151 questionsThe capacity requirements plan is used primarily to balance capacity and load at work centers. A work center is a location where one or more resources perform a specific operation or a group of operations. Capacity is the amount of time or output that a work center can offer for production activities. Load is the amount of time or output that a work center is required to produce based on the planned production schedule. Balancing capacity and load means matching the available capacity with the required load, so that there is no excess or shortage of capacity at any work center. The capacity requirements plan is a report that shows the projected load and capacity of each work center over a planning horizon. It is derived from the master production schedule (MPS), which specifies the quantity and timing of finished goods to be produced, and the bill of materials (BOM), which specifies the components and materials needed for each finished good. The capacity requirements plan also uses the routing file, which specifies the sequence of operations and work centers required for each finished good, and the work center file, which specifies the capacity and availability of each work center. The capacity requirements plan can help to identify any gaps or surpluses in capacity at each work center and to take corrective actions, such as revising the MPS, rescheduling operations, adding or reducing resources, or outsourcing production. The other options are not the primary uses of the capacity requirements plan. Calculating the level of available capacity is an input to the capacity requirements plan, not an output. The level of available capacity is determined by the work center file, which contains information such as shifts, hours, efficiency, utilization, and maintenance of each work center. Determining the overall product load profile is not a use of the capacity requirements plan, as it does not consider the product mix or demand variability. The overall product load profile is a general estimate of the total production volume or demand over a period of time. Determining the priority of orders is not a use of the capacity requirements plan, as it does not consider the due dates or urgency of orders. The priority of orders is determined by using priority rules or dispatching methods, such as first-come-first-served (FCFS), shortest processing time (SPT), earliest due date (EDD), or critical ratio (CR). Reference := Capacity Requirements Planning (CRP): Definition and Procedures, Capacity Requirements Planning (CRP Plan and Strategies) - ERP Information, Definition of Capacity Requirements Planning (CRP) - Gartner …
Keep practicing
Take the free CPIM-PART-2 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CPIM-PART-2 practice questions
- Question 1In a lean environment, one uses material requirements planning (MRP) processing primarily…
- Question 2Up-to-date information about production order status is required to do which of the follo…
- Question 3The results from responding to uncertainty in the supply chain by exaggerating lead times…
- Question 5Which of the following outcomes is a benefit of mixed-model scheduling?
- Question 6Which of the following tools is used to evaluate the impact that a production plan has on…
- Question 7The demonstrated capacity of equipment in a process flow is $1,200 per day. Due to a malf…
