[Developing AV Solutions]After there is an approved labor change to a project, what should the project manager do NEXT?

Full set: 254 questions

[Developing AV Solutions]

After there is an approved labor change to a project, what should the project manager do NEXT?

Answer options
A: update the schedule Correct answer
B: order the equipment
C: issue an invoice for the change
D: inform the purchasing department
Correct Answer:
A. update the schedule
Explanation

In project management, once a change order affecting labor, scope, or materials is formally approved, the project manager's immediate next step is to update the project management plan. This includes revising the project schedule to reflect the change in labor allocation and duration, as well as updating the budget and scope documents. This ensures that all project documentation reflects the new, approved baseline, and all team members are working from the current plan. Failure to update the plan immediately can lead to confusion and misalignment.

Why Incorrect

B. The change is for labor, not necessarily equipment. Even if equipment were involved, updating the master project plan would still be the first administrative step.
C. Invoicing for a change order is a financial activity that typically occurs based on contract terms, not necessarily immediately after approval of the change itself.
D. Informing the purchasing department is only necessary if the labor change requires procurement (e.g., a new subcontractor), and it would follow the update to the overall project plan.

References

1. AVIXA. (2020). CTS Certified Technology Specialist Exam Guide, Third Edition. McGraw-Hill. Chapter 8, "Managing the Project," describes the change order process. Once approved, "the project manager should update the project documentation to reflect the change" (p. 278).

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK Guide), Seventh Edition. Section 4.6, "Perform Integrated Change Control," states that the output of an approved change request is an update to the project management plan and project documents.