CTS practice question 8 of 35
[Developing AV Solutions]After there is an approved labor change to a project, what should the project manager do NEXT?
Full set: 254 questions[Developing AV Solutions]
After there is an approved labor change to a project, what should the project manager do NEXT?
In project management, once a change order affecting labor, scope, or materials is formally approved, the project manager's immediate next step is to update the project management plan. This includes revising the project schedule to reflect the change in labor allocation and duration, as well as updating the budget and scope documents. This ensures that all project documentation reflects the new, approved baseline, and all team members are working from the current plan. Failure to update the plan immediately can lead to confusion and misalignment.
B. The change is for labor, not necessarily equipment. Even if equipment were involved, updating the master project plan would still be the first administrative step.
C. Invoicing for a change order is a financial activity that typically occurs based on contract terms, not necessarily immediately after approval of the change itself.
D. Informing the purchasing department is only necessary if the labor change requires procurement (e.g., a new subcontractor), and it would follow the update to the overall project plan.
1. AVIXA. (2020). CTS Certified Technology Specialist Exam Guide, Third Edition. McGraw-Hill. Chapter 8, "Managing the Project," describes the change order process. Once approved, "the project manager should update the project documentation to reflect the change" (p. 278).
2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK Guide), Seventh Edition. Section 4.6, "Perform Integrated Change Control," states that the output of an approved change request is an update to the project management plan and project documents.
Keep practicing
Take the free CTS practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CTS practice questions
- Question 1[Developing AV Solutions]Which method of control is supported by HDBaseT?
- Question 2[Conducting a Needs Assessment] During a site survey, a client states that there will be …
- Question 3[Developing AV Solutions] According to AVIXA Standards, what is the MINIMUM load rating f…
- Question 4[Developing AV Solutions] What key specification of an owner furnished credenza will a te…
- Question 7[Developing AV Solutions] In an audiovisual system where a touch panel is to be connected…
- Question 9[Developing AV Solutions]When an audio device can no longer accurately reproduce the audi…
