DCDC-004 practice question 10 of 10
Which activity belongs to project closeout?
Full set: 162 questionsProject closeout is the final phase of project management where all deliverables are finalized and operational handover occurs. Core closeout activities include completing punch-list items, resolving outstanding installation deficiencies, transferring owner training materials, delivering warranties, and submitting approved final record (as-built) drawings and operations and maintenance (O&M) manuals to the facility owner.
B. Parcel selection is an initial site selection and feasibility activity occurring during project initiation, not closeout.
C. Defining business requirements occurs during the initial planning and programming phase before design work begins.
D. Conducting a site search is a preliminary feasibility activity undertaken long before project execution or closeout.
1. ANSI/BICSI 002-2019, Data Center Design and Implementation Best Practices, Section 17.5: Project Finalization and Closeout.
2. Project Management Institute (PMI), A Guide to the Project Management Body of Knowledge (PMBOK Guide), 7th Edition, Section 2.8: Project Closeout.
3. BICSI Telecommunications Distribution Methods Manual (TDMM), 14th Edition, Chapter 20: Project Management, Section: Closeout Phase.
Keep practicing
Take the free DCDC-004 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other DCDC-004 practice questions
- Question 1What does mechanical-system redundancy protect against?
- Question 2What is the purpose of structured cabling?
- Question 3What is the purpose of electrical grounding and bonding?
- Question 5How should future expansion space be protected in the layout?
- Question 6Why should planning assumptions be documented?
- Question 7How should a discovered nonconforming installation be handled?