ECBA practice question 13 of 25

In which requirements prioritization factor would time-to-market scenarios apply?

Full set: 210 questions
Answer options
A: Time sensitivity Correct answer
B: Stability
C: Cost
D: Regulatory or policy compliance
Correct Answer:
A. Time sensitivity
Explanation

Time-to-market scenarios are driven by the need to release a product or feature within a specific timeframe to capture a market opportunity or gain a competitive advantage. This directly aligns with the prioritization factor of Time Sensitivity. This factor assesses the urgency of a requirement and how its value diminishes over time. A requirement with high time sensitivity must be implemented by a certain date to realize its full benefit, which is the core principle behind time-to-market strategies.

Why Incorrect

B. Stability: This factor refers to the likelihood that a requirement will change, not the urgency of its implementation.
C. Cost: This pertains to the financial resources required to implement a requirement, which is distinct from the temporal urgency of its delivery.
D. Regulatory or policy compliance: This prioritizes requirements based on the need to adhere to laws or rules, which is a different driver than seizing a market opportunity.

References

1. International Institute of Business Analysis. (2015). A Guide to the Business Analysis Body of Knowledge (BABOK Guide) (Version 3). IIBA.

Section 5.3.4.1

Basis for Prioritization: This section lists "Time Sensitivity" as a key basis for prioritization. It is described as the urgency of the requirement

often driven by a specific deadline

after which the value of the requirement is greatly reduced. This directly encompasses time-to-market scenarios. The same section also defines Stability

Cost

and Regulatory or Policy Compliance as separate and distinct factors.