FSL-201 practice question 22 of 25
Service appointments in a “cannot complete” status may indicate that an additional part or expert assistance is needed to complete the work. Universal containers defined that service appointments in a “cannot complete” status are unable to be rescheduled or unscheduled for history tracking purposes. Which two items should the consultant recommend to meet the requirement? Choose 2 answers
Full set: 163 questionsCorrect Answer:
B. Define “cannot complete” as a pinned status for scheduling and optimization services.; C. Ensure that status transitions are configured to prevent the update from “cannot
complete” to “none’.
Explanation
Pinned statuses prevent service appointments from being rescheduled or unscheduled by scheduling and optimization services3. Status transitions define the valid status changes for service appointments based on business rules.
Reference: 3 https://help.salesforce.com/s/articleView?id=sf.fs_pinned_statuses.htm&type=5 https://help.salesforce.com/s/articleView?id=sf.fs_status_transitions.htm&type=5
Keep practicing
Take the free FSL-201 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other FSL-201 practice questions
- Question 1Universal Containers wants to ensure that Service Appointments are dispatched to Resource…
- Question 2Universal Containers has customers who have previously negotiated pricing on some product…
- Question 3Which two considerations impact the scheduled timeframe of Multi-day Work? Choose 2 answe…
- Question 4Universal Containers wants to limit their Technicians’ view of Work Orders and Service Ap…
- Question 5Universal Containers (UC) wants to schedule Work Orders only if Technicians have the nece…
- Question 6Each door lock that Universal Containers (UC) sells has a unique 20 digit code. The code …