IDPX practice question 17 of 25

During an office renovation, a financial firm wants to continue occupying the space while maintaining daily functions. What is the BEST method for the designer to follow?

Full set: 175 questions
Answer options
A: Utilize fast-track scheduling for completion of the space as a whole
B: Create separate permits for each area to be completed independently
C: Designate one portion of the space to be completed prior to another beginning Correct answer
Correct Answer:
C. Designate one portion of the space to be completed prior to another beginning
Explanation

The most appropriate method for a renovation where the client must remain operational is phased construction. This strategy involves dividing the project into distinct geographical or functional stages. By completing one designated portion of the space first, the client can relocate their operations into the newly finished area. This allows construction to proceed in the vacated portion, thereby minimizing disruption to the firm's daily business functions and ensuring continuity. This sequential approach is the standard and most effective way to manage construction within an occupied commercial space.

Why Incorrect

A. Fast-track scheduling overlaps design and construction to shorten the total project duration but does not inherently manage the logistics of an occupied space.
B. Creating separate permits is an administrative process related to regulatory approval, not a strategic method for managing construction and client occupancy.

References

1. Piotrowski

Christine M. Interior Design Management: A Handbook for Designers and Their Clients. 2nd ed.

John Wiley & Sons

2014

p. 218.

In Chapter 11

"Project Management

" the text states

"When a project involves remodeling

it is often necessary to complete the project in phases so that the client can continue to use the facility. For example

in a large office facility

one floor or one department might be remodeled at a time." This directly supports the concept of phased construction for occupied renovations.

2. Piotrowski

Christine M. Professional Practice for Interior Designers. 6th ed.

John Wiley & Sons

2017

pp. 438-439.

Chapter 16

"Contract Administration: Construction and Order Installation

" discusses project scheduling. It emphasizes the need for careful coordination

especially when a client needs to occupy the space

noting that work may need to be done in phases to accommodate the client's ongoing operations.

3. Karlen

Mark

and Rob Fleming. Space Planning Basics. 4th ed.

John Wiley & Sons

2016

Chapter 10.

This chapter

"The Design Process in Practice

" discusses the complexities of project execution. It implicitly supports phasing as a solution for complex client requirements

such as the need for continued occupancy

which requires breaking down the project into manageable parts to avoid disrupting the client's core business.