ISEB-PM1 practice question 3 of 35

Planning activities such that predetermined resource availability pools are not exceeded is called:

Full set: 625 questions
Answer options
A: Manpower planning.
B: Manpower leveling.
C: Resource leveling.
D: Manpower contingency planning.
E: Resource limited planning. Correct answer
Correct Answer:
E. Resource limited planning.