ISEB-PM1 practice question 6 of 35

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Full set: 625 questions
Answer options
A: 1.00
B: 0.40
C: 0.50
D: 0.80 Correct answer
Correct Answer:
D. 0.80