ISEB-PM1 practice question 5 of 35

Which of the following is NOT a reason to measure variances from the baseline?

Full set: 625 questions
Answer options
A: To catch deviations early
B: To allow early corrective action
C: To determine if there are any wild fluctuations
D: To create a project control system Correct answer
Correct Answer:
D. To create a project control system