ISO-22301-LEAD-AUDITOR practice question 17 of 35

Which of the following is about planning and arrangement of BCM tasks into a proper order of relationship to achieve the defined outcomes?

Full set: 100 questions
Answer options
A: Communication
B: Analysis
C: Coordination Correct answer
D: Performance
Correct Answer:
C. Coordination
Explanation

Coordination in the context of Business Continuity Management involves the systematic planning, arrangement, and synchronization of BCM tasks and resources into a logical sequence. This ensures that interrelated activities, such as incident response, disaster recovery, and business resumption, are executed in the proper order to achieve the defined recovery time objectives (RTOs) and overall BCMS outcomes. Effective coordination prevents resource conflicts during a disruption.

Why Incorrect

A. Communication: Deals with the exchange of information and stakeholder awareness, not the sequential arrangement and synchronization of operational tasks.
B. Analysis: Involves evaluating risks and business impacts (e.g., BIA) to determine requirements, not arranging the execution order of BCM tasks.
D. Performance: Relates to evaluating the effectiveness and metrics of the BCMS (Clause 9), rather than the planning and arrangement of tasks.

References

1. International Organization for Standardization. (2019). ISO 22301:2019 Security and resilience — Business continuity management systems — Requirements. Clause 8.1 (Operational planning and control).

2. Business Continuity Institute (BCI). (2018). Good Practice Guidelines (GPG). Module 5: Implementation (focusing on the coordination of response structures).