Which phase determines potential issues pertaining to the management of the BCMS?

Full set: 100 questions
Answer options
A: Plan
B: Do
C: Check Correct answer
D: Act
Correct Answer:
C. Check
Explanation

The Check phase monitors and reviews BCMS performance against policy and objectives, including audits and management review. This phase identifies issues, deficiencies, and opportunities requiring remediation or improvement before actions are taken in the Act phase.

Why Incorrect

A. Plan: Establishes the BCMS framework, objectives, and processes; it is not the monitoring/review phase.
B. Do: Implements and operates BCMS processes and controls.
D. Act: Addresses identified issues through corrective action and improvement, after they are detected.

References

- ISO 22301:2012, Introduction, Table 1 “Explanation of PDCA model” — Check: monitor and review performance, report results, determine actions.

- ISO 22301:2019, Clause 9.1 — monitoring, measurement, analysis, and evaluation.

- ISO 22301:2019, Clauses 9.2–9.3 — internal audit and management review.