L4M2 practice question 7 of 30
A procurement manager is writing a conformance specification for a non-core component. She thinks that if the requirements in specification are higher than ISO standards, her company can achieve greater cost-savings. Is the procurement manager’s opinion correct?
Full set: 301 questionsThe procurement manager's opinion is incorrect. Setting a specification higher than a recognized international standard (like ISO) for a non-core component is known as over-specification. This practice typically increases costs rather than creating savings. Suppliers may need to use more expensive materials, implement more complex manufacturing processes, or conduct more rigorous testing to meet these elevated requirements. These additional efforts result in higher production costs, which are subsequently passed on to the buying organisation. True cost-effectiveness is achieved by specifying requirements that are fit for purpose, not by exceeding them unnecessarily, which undermines the principle of value for money.
B. Higher and more niche requirements reduce the number of capable suppliers, thereby weakening the buyer's bargaining power, not strengthening it.
C. The premise that the manager's opinion is correct is false. Furthermore, while optimising specifications is crucial for value for money, it is not the only method.
D. The premise is incorrect. A supplier meeting unnecessarily high requirements may be technically capable but is also likely to be more expensive, not necessarily the "best" overall. ---
1. Baily
P.
Farmer
D.
Crocker
B.
Jessop
D.
& Jones
D. (2015). Procurement
Principles & Management (11th ed.). Pearson Education. In Chapter 6
'Specification'
it is stated that "Over-specification
where the specifier is over-cautious or 'gold-plates' the specification
adds cost without adding value" (p. 119). This directly supports the reasoning that higher specifications incur additional costs.
2. CIPS (2018). L4M2 Defining Business Need: CIPS Level 4 Diploma in Procurement and Supply. Profex Publishing Limited. Chapter 3
'Developing Specifications'
discusses the potential problems with specifications
highlighting that over-specification can "increase costs" and "restrict competition" (pp. 84-85). This confirms that the manager's approach would lead to higher costs
not savings.
3. Lysons
K.
& Farrington
B. (2020). Procurement and Supply Chain Management (10th ed.). Pearson. Chapter 11
'Specifying and Managing Quality'
explains that specifications should be appropriate for the intended purpose. The text implies that demanding a quality level beyond what is required (e.g.
exceeding an ISO standard for a non-core item) leads to unnecessary expense
contradicting the goal of value for money (p. 287).
Keep practicing
Take the free L4M2 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other L4M2 practice questions
- Question 1An IT category buyer wishes to include social and environmental criteria within a supplie…
- Question 2Which of the following are typical environmental considerations throughout the contract l…
- Question 3Which of the following problems may be identified as open-ended problems? Select TWO that…
- Question 4Which of the following is the core of value analysis process?
- Question 5Which of the following statements is true about product life cycle?
- Question 6A procurement manager consolidates the company expense on printing and office supplies in…