L4M2 practice question 12 of 30

After a project, the procurement team at CLK Ltd meets up and summarises on the performance. They see that they actually spent $5,000 less than…

Choose your answer, then check it against the explanation.

After a project, the procurement team at CLK Ltd meets up and summarises on the performance. They see that they actually spent $5,000 less than planned budget. The team tries to identifies why there is such difference. This activity is known as...?